Evaporation
After the vacuum chamber has reached adequate pressure
(
), the IC6000 has been programed
(Section 3.8), and the high voltage system has been
initialized (Section 3.7), you are ready to begin
evaporation. You should do the following:
- Go to the IC6000 ``Data'' screen by pressing ``Disp'' followed by ``8''
- Select the recipe you programmed by pressing ``FLM#'' followed
by the recipe number (note that the buttons are quite sticky. Make
sure that the ``FILM: `` indicator at the bottom of the screen changes
to the proper film number)
- Update your log entry with the proper ``XTAL Value'' and ``Base
Pressure'' (Section 3.3).
- On E-beam 2, turn the ion gauge sensitivity to the minimum (
) position.
At this point, you are ready to begin evaporation. Evaporation can be
performed either automatically or manually.
Subsections
Collin W. Hitchcock
2002-02-28